Building or Renovating in Myoko: When You Need Building Confirmation
This guide is for people in Australia or elsewhere who own, or plan to buy, a house in Myoko and want to build, extend or renovate it. In Japan, many building projects need an official check of the plans before work starts. This is called building confirmation (kenchiku kakunin). The rules changed in April 2025, and many renovations of two-storey wooden houses now need it. Below we explain which works need confirmation, which do not, and who handles it for Myoko.
Everything here comes from pages and leaflets of the Ministry of Land, Infrastructure, Transport and Tourism (MLIT) and Niigata Prefecture. All were read on 24 November 2026. This is general information only. Whether your own project needs confirmation is decided case by case, so ask a licensed architect (kenchikushi) or the building office before you start.
What building confirmation is
Before certain building works, the owner must apply to have the plans checked against the Building Standards Act. The check is done by a building official (kenchiku shuji) or by a private designated inspection body. MLIT says the process must be finished before work begins.
The penalties are real. MLIT says an owner who fails to apply for confirmation or for the completion inspection can face up to one year in prison or a fine of up to ¥1 million. The same applies to a builder who starts work without a confirmation certificate.
What changed in April 2025
Japan used to have a special rule for small wooden buildings, often called the "No. 4 exemption" (yongo tokurei). Under it, two-storey wooden houses were treated as small buildings. Their structural checks could be skipped when an architect designed them, and big renovations did not need confirmation.
From 1 April 2025, MLIT split these buildings into two new groups:
- New Category 2: buildings with two or more storeys, or with more than 200 square metres of floor space in total. This covers most two-storey wooden houses. They now need confirmation and inspection in every area, including outside city planning areas. This also applies to large renovations. The structural check is no longer skipped.
- New Category 3: single-storey buildings of 200 square metres or less. These need confirmation when built inside a city planning area or similar zone. Some plan checks can still be skipped, as before.
Niigata Prefecture gives the same summary on its own page. For new Category 2 buildings, applications must now include structural and energy-efficiency drawings. The new rules apply to works that start on or after 1 April 2025.
Renovations: the "more than half" test
For a two-storey wooden house, the question is whether the work is a "large repair" or "large remodelling" under the Building Standards Act. MLIT defines this as work on more than half of one or more of the main structural parts. These parts are the walls, columns, floors, beams, roof and stairs.
MLIT measures "more than half" separately for each part:
- Walls: share of the total wall area
- Columns and beams: share of the total number
- Floors and roof: share of the total area seen from above
- Stairs: share of the stairs on each floor
MLIT also lists what does not count as a main structural part. This includes walls that are not structurally important, small studs, eaves, the lowest floor and outdoor stairs.
MLIT's examples: replacing a staircase or fully rebuilding the roof needs confirmation. Changing only the roof or wall finishes does not.
Works that do not need confirmation
MLIT's leaflet and its guide to renovation cases say these works do not need confirmation:
- Replacing a kitchen, toilet or unit bath
- Fitting handrails or ramps for accessibility
- Changing only partition walls that are not structurally important
MLIT's 2025 explanation adds more detail on roofs and outer walls:
- Replacing only the roof covering, or laying a new roof over the old one, is generally not a large repair.
- Replacing only the outer cladding, or adding insulation from inside the wall, is generally not a large repair either.
- However, if the work ends up replacing every layer of the roof or wall, and that covers more than half, it can count.
MLIT says some works may still count as large renovations, depending on what is done. It advises asking the building official or a designated inspection body. It also notes that even when no confirmation is needed, the house must still meet the Building Standards Act after the work.
Old houses: extra work may be needed
Many houses in Myoko are old. MLIT notes that when a renovation goes through confirmation, any parts of the house that do not meet the current law may also need to be brought up to standard. This can add to the cost and the scope of the work, so it is worth raising with your architect early.
MLIT also says a licensed architect must design and supervise a large renovation of a building over 100 square metres. It adds that prefectures may set their own floor-area limits.
Who handles building confirmation for Myoko
Niigata Prefecture says six cities in the prefecture have their own building officials. Myoko is not one of them. For Myoko, the prefecture's Joetsu Regional Development Bureau (Building Section, in Joetsu City) handles work under the Building Standards Act. Its pages say:
- Applications for confirmation are handed in at the city where the building stands. For a Myoko house, that is Myoko City.
- The bureau's fee section points to Niigata Prefecture revenue stamps, sold at places such as the bureau's shop and some banks. Since June 2022, applications can also be made through the prefecture's online system, with card payment.
- The bureau asks people to book a time for an advance consultation, and to send drawings ahead.
You can also apply to a private designated inspection body instead of the official.
Snow and other local design rules
The bureau's page lists local data that designers must use. Two points stand out for Myoko:
- Heavy snow area. The whole area the bureau covers is designated as a heavy snow area. The design snow depth is set at between 130 cm and 300 cm, depending on location. Each 1 cm of snow must be counted as at least 29.4 N per square metres of load.
- Zoning. Parts of Myoko have land-use zones and a quasi-fire-prevention district. Parts are also in a scenic zone (the Namikayama Scenic District) and in landslide special alert zones. The bureau says to ask the city for details.
The same page also lists other rules that may apply, such as the Farmland Act and the Natural Parks Act. Building inside the national park has its own permit system, which we cover in a separate guide.
Demolishing a building
The bureau also lists notices for pulling a building down:
- For demolition of more than 10 square metres, the builder must notify the city before starting.
- For demolition of a building of 80 square metres or more, a notice under the Construction Recycling Act must be filed at least seven days before work starts.
- The bureau asks for a survey for asbestos in building materials before demolition.
What we could not verify, and therefore left out
- The exact fees for building confirmation. The bureau links to a fee list that we did not check.
- How long confirmation takes. The pages we read do not say.
- Whether Niigata sets its own floor-area limits for architect-only work. MLIT says prefectures may do so, but we did not find Niigata's rule.
- Exactly where Myoko's city planning area and zones begin and end. Check the address with Myoko City.
- Small extensions. Special rules apply to some small additions, but we did not find a primary source to quote, so we left them out.
Related guides
- Old Houses in Myoko and the 1981 Earthquake Standard
- Building or Renovating Inside Myoko-Togakushi Renzan National Park
More from the Journal
Browse every guide in the Myoko Kogen Journal. This guide is general information, not legal or architectural advice.
Sources
All URLs retrieved 2026-11-24.
- MLIT — 建築基準法改正 建築確認(2025年3月版 leaflet on large renovations: Category 2 and 3, the more-than-half test, kitchen/toilet/bath and handrail works, confirmation before work, current-law upgrades, architect for over 100 square metres, penalties): https://www.mlit.go.jp/common/001765901.pdf
- MLIT — リフォームにおける建築確認要否の解説事例集(木造一戸建て住宅) (how "more than half" is measured for each part, what is not a main structural part, works that never need confirmation, compliance even without confirmation): https://www.mlit.go.jp/common/001853472.pdf
- MLIT — 木造戸建の大規模なリフォームに関する建築確認手続について (old and new categories, roof covering and cover-over roofs, outer cladding and inside insulation): https://www.mlit.go.jp/common/001766698.pdf
- MLIT — 「4号特例」が変わります (what the No. 4 exemption was; structural and energy drawings now required; new Category 3 inside city planning areas): https://www.mlit.go.jp/common/001500388.pdf
- Niigata Prefecture — 建築基準法・建築物省エネ法の改正について(令和7年4月1日施行) (two or more storeys or over 200 square metres need confirmation in all areas, including large renovations): https://www.pref.niigata.lg.jp/site/jutaku/kaiseikijunnhou2025.html
- Niigata Prefecture — 新潟県の建築課の所管区域 (Joetsu bureau covers Myoko; six cities with their own building officials): https://www.pref.niigata.lg.jp/sec/jutaku/1197216943238.html
- Niigata Prefecture, Joetsu Regional Development Bureau — 建築課のページ (Myoko under the bureau for the Building Standards Act, fees and revenue stamps, online applications, advance consultation, zoning, heavy snow data, other laws): https://www.pref.niigata.lg.jp/sec/jouetsu_seibi/kenchiku-index.html
- Niigata Prefecture, Joetsu Regional Development Bureau — 建築工事着手前の諸手続きについて (confirmation applications go to the city; demolition notices; asbestos survey): https://www.pref.niigata.lg.jp/sec/jouetsu_seibi/1356837340640.html
Header photo: “A grassy ridge on Mount Amakazari with cloud rolling through the valleys below” (Ministry of the Environment, Japan / 環境省), https://www.env.go.jp/nature/nationalparks/list/myoko-togakushi-renzan/spot/. Edited (cropped and resized) for use as the header image on this page. Used under the Public Data License (PDL) Version 1.0.